Main page
[SOLUTIONS] [DOWNLOAD] [ORDERING] [SUPPORT] [PRESS] [PARTNERS] [TESTIMONIALS] [ABOUT US]

work done last week

work done last week

 
Hello,

See, my boss wants to see what I was doing, say, from June 5 to June 13. How do I make such a report using Outlook Task? I don’t get it, because I need not only the tasks which I completed, but also those I didn’t start for example. How do I go about it?

Thanks,
Brian

work done last week -- original topic

 

 
Hi, Brian

Quote: See, my boss wants to see what I was doing, say, from June 5 to June 13. How do I make such a report using Outlook Task? I don’t get it, because I need not only the tasks which I completed, but also those I didn’t start for example. How do I go about it?


OK, I guess, the main problem here is to make sure you get the start dates correct. So, in your case you need to have all the tasks relating to a certain project that started before June 5. So while fetching tasks set the following parameters in the Fetch Tasks dialog box:

Start date - to June 5
Subject or Content – name of your project

Make sure you include Percent complete column in your results fields (select Fetch Tasks , then Options . In the Results Fields tab choose Percent complete ). That will show which stage of the task you’re on.

-- original topic

 

 

Made in Devoler Copyright © 2000-2005 AKS-Labs. All rights reserved.